Falsification of documents.. Pls. Nid help po

2 posters

Go down  Message [Page 1 of 1]

Kitschler


Arresto Menor

Nagpatayo po ako ng bahay. Tapos Po yung dating kaklase ko may nirecommend na engr. at contractor na din. Pagkatapos po gumawa ng contract umalis na po ako papunta ibang bansa. Nag-uusap na lng po kami sa email about dun sa progress ng project. Khit hindi p tapos yung bahay, hiningi nya na yung kalahati nung last payment na dapat Po yun ibigay pag tapos na yung bahay kc yung nkalagay sa kontrata. Pero binigay ko p rin para lng wala ng gulo at matapos na yung bahay ko. Pag-uwi ko nakita ko na marami syang hindi sinunod sa kontrata. Katulad ng: dapat may peebles yung finishing ng bahay at yung ceiling ng bahay nag crack na. Pero khit ganun binayaran ko p rin para wala ng gulo. Pagtanggap nya ng last payment masyado sya excited at hindi na naalala yung maniwang equipments nya dun sa loob ng property ko. After 2 weeks bumalik sya at gusto kunin yung gamit nya. Hindi ko pinabigay kc yung linya ng kuryente temporary p lng at hindi p tapos yung obligation nya. After 3 months inasikaso ko na yung certificate of occupancy at nakita ko na May dapat p sya pirmahan dun. Dahil hindi na sya mahagilap at ayoko na din na may contact p sa kanya, nagpahanap ako ng tao na pwede gumaya sa pirma nya para matapos na yung papers nung bahay ko. Khit yung electrical plan nya na mali ako na rin nagpabago at nagbayad ulit. Nung irelease na sana ng city hall yung occupancy permit hinarang nya at pinahold yung building permit kc daw hindi nga sya ang pumirma nun. Ano po b yung punishment kung napatunayan na pinagaya ko yung pirma nya? Malakas Po b yung kaso nya? Ano Po pwede ko gawin? Yung dineclare nya din po ng price ng bahay sa city hall ay halos kalahati lng nung totoong price na nasa kontrata para maliit lng yung mabayaran nya na tax. Pwede ko din po b syang isumbong sa BIR or city hall na nandaya sya? Ano po b yung pwede gawin sa legal na paraan. Maraming salamat po.

Kitschler


Arresto Menor

Nagpablotter din po sya about dun sa gamit nya na nasa loob ng property ko. May right p b sya na kunin yung gamit nya? Thank u po ulit.

raheemerick

raheemerick
Reclusion Perpetua

own opinion lng sir.. wag nyo po i hold ang equipment nya na naiwan sa bakuran nyo. bka makasuhan pa kau nyan:) sa isang banda wla kau any papers na kasunduan na may kaugnayan sa gamit nya na nasa bakuran mo. halimbawa sana kung naka prenda yan sa inyo sa atraso nya or naka sanla. but anyway.. may posible kau kaso na pwdeng harapin sa falsification ng pirma nya. once it proven? harapin nyo na lng.

then gather ka naman ng mga iregularity nya na ginagawa gaya ng false dec ng amount sa cityhall sa project nya sa inyo. and dapat may o.r sya na isue sa inyo each time may payment na nagaganap. or else BIR ang magiging problema nya. then dapat naka saad sa contrata ang work durations ng proj. and naka saad din ang penalty kapag hndi nya na meet ang deadlines. dpat naka saad din sa contract ang mga fine materials na gagamitin nya. approved by the contractor and the client. then kapag may hndi nasunod don? pwde nyo yun magamait againts to him. even the approve plan drawings dapat masunod din unless may conxent ng engr or client ang revisions. kung madami sya hndi nasunod sa contrata and project? gather all this and file a case againts him. then mas maganda if ipa stenght test mo pa ang bahay mo. kasi nakalagay din sa contrata dapt ang concerete mixture and psi ng concrete works. and once it failes? pananagutan nya yun sa city hall:) sa madaling sabi. hanapan mo ng butas at cguraduhing approved and listed ang mga yan sa pinirmahan mong kontrata.

note. i just tell you this para sa counter charge mo sa kanya. kc pag mas madami ka maikaso sa kanya? bka sya mismo ang lumapit sau to setle this thing down. Smile

raheemerick

raheemerick
Reclusion Perpetua

example po nung sinsabi qng strenght test.. kung naka saad sa contarta. at dapat naman talaga:) each beams and columns and live load slabs must be in a concrete mixtures of 1:2:3 or let says.. 5000psi.. since ang contractor madalas hndi sinusunod yan lalo na pag wla naman mag sasagawa ng strenght test:) instead na 1:2:3? ginagawa nila minsan 1:3:4. hndi sinusunod ang nasa contarata. kasi.. jan sila makaka tipid ng materials and filled there pockets:) no ofens sa mga ibang contractor ha. di q naman nilalahat:) im just giving mr. kits idea na pwd nya i counter. and once ma prove na hndi nya sinunod ang nasa contrata according sa dapt na psi strenght nito? kawawang contractor yan at malaki pananagutan nya:) i know hndi related sa post nys sinsabi q. as i said lng. im giving him ideas para maka pag counter if ever para may justice naman ang gastos nya...

good clients deservs a good service:)

Kitschler


Arresto Menor

Thank you very very much sa advice nyo po..

Kitschler


Arresto Menor

Sino po pwedeng gumawa nyang strength test? Mga tao sa city hall din po b yan? Thank u.

raheemerick

raheemerick
Reclusion Perpetua

actualy sa mga engineering laboratory conduct yang strenght test na yan.. if you notice sa mga bog construction project. nag sasagawa ng surprise visit ang mga taga city hall while concrete pouring ang activity ng contractor. kc gusto nila yung hindi prepare ang contractor or foreman. then kukuha sila ng actual na concrete mix sa curent mix nila as a sample para sa concrete strengh test. and once bagsak at dinaya ng contractor or foreman ang halo? ipinatitigil ang construction. kc the client will take the risk at delikado pag bagsak sa strenght test ang isang construction. remember sa news yung 3 storey residence na bumigay sa napaka hinang earth movement? ipinasuri ang concrete strenght nito kc weak daw ang form at structure. then ayun. bagsak nga sa strenght test. then ofcorx. sagutin yun ng contractor kasi hindi nya sinunod ang contrata.. since wla kasi supervisor sa side ng client. kaya si contractor. sub-standard na nga mga steel bars nya? under size pa ang mga beams nya. and the concrete mix is very weak. tinipid sa cement:)

yes po. if im not mistaken pwde sa city hall mag request ng ganyan.

it happen to me kasi b4 yung ganyan eh. we have a contractor and 3 storey res. yung project. nagkataon naman na nasa side ako ng client which is nasa ibang bansa kasi sya. in the midle of construction lng ako umeksena kasi naka ramdam yung client na di maganda sa contractor.. then iyon i started to invistigate. tinanong q mismo yung mga labor. during conc. poring nila sa mga poste at beams. pano halo nila? sabi nung mga labor. utos daw ng boss nila (contractor) 1:3:4 minsan daw 1:3:5 pa.. then i start to conversate with this contractor. pero todo deny sya at pinagalitan pa yung labor.. xempre malay nga naman ni labor sa mga mix mix na ganyan diba? then the folowing days nag tanong aq ulit. ayun.. 1:2:3 na ang sagot ni labor.

pero since mukang galit kay contractor yung isang labor. ang instruction daw sa kanila ay ganto..

pag anjan si raheem, 1:2:3 mix na gawin nyo. pero pag wla sya? 1:3:4 ok?

ayun. nag hindi ako advice sa cityhall at pina strenght test namin.

result??? bagsak!! kya ayun. problemado si contractor dahil di sya pinalampas ni client.